company: Universidad de Chile
creator: D. Espinoza
description: |
  Unit commitment problems (electricity production planning problems) coming from the Chilean electricity system, they have either one or two week planning horizons, and include constraints on minimum on-off time for the power plants, ensure some reserve energy in the system, and minimize global operation costs.
email: daespino@gmail.com
license: ''
misc: |
8
  Imported from MIPLIB2010.
9 10 11 12
name: Daniel Espinoza
other-license: ''
owner: ''
source: ''